Client
Housing Developer
Sector
Residential
Project Type
Drainage CCTV
Products Used
N/A
Onsite Duration
0.5 days
Location
London
REQUIREMENTSA pumping station was found not to be discharging at all. It appeared that the rising main had become blocked outside of the pumping station. The customer requested an immediate full investigation to prevent flooding. As this was an already completed construction project, minimal disruption was required. METHOD• The pumping station was disconnected at high level and we checked that the pumps were discharging correctly. RESULTS• Groundworkers excavated under the resin drive to prevent damage to the driveway |
|